Equinox Projects

West Doe Sour Gas Plant (100 MMscfd)

West Doe Sour Gas Plant (100 MMscfd)

Project Summary:

FEED & Detail Design for a sour gas plant with three process trains totaling 100 MMscfd with process gas conditions of 2.6% H2S and 3.0% CO2 from the Montney. Facility includes containing inlet separation, inlet compression, amine sweetening, refrigeration, liquid fractionation and stabilization, acid gas compression, vapour recovery and recycle system, sales compression. Power generation includes one Solar Taurus 59 (4500 KW) genset and five 550 KW natural gas driven electrical generators). Also includes storage for produced water, condensate and NGL with truck-out facility.

Equinox provided FEED & Detail Design for a sour gas plant with three process trains totaling 100 MMscfd.